The World’s First Floating Wind Farm Approved by Norwegian Authorities

floating wind power farm

writer icon Carsten Kristensen     Equinor   |   Sustainability     🕐 14. Apr. 2020


The Ministry of Petroleum and Industry has approved the plans for development and operation of the world’s first floating wind farm, Hywind Tampen.

Floating Wind Power
Hywind Tampen will be an 88 MW floating wind power farm created to provide electricity for the Snorre and Gullfaks offshore field operations in the Norwegian North Sea.

The Approval
On 11 October 2019, Equinor and the Snorre and Gullfaks partners submitted two updated plans for development and operation to Norwegian authorities.

“Hywind Tampen is a pioneering project and a central contribution to reducing emissions from Gullfaks and Snorre, and I am pleased that both ESA and Norwegian authorities have approved the project,” said Arne Sigve Nylund, Equinor’s executive vice president for Development & Production Norway.

“We are experiencing very challenging times, and we are focusing on continuing our transition effort while attending to and developing the value on the Norwegian continental shelf and at the same time reducing the climate footprint from our operations,” Sigve Nylund added.

Reducing CO2 Emissions
By reducing the use of gas turbines on the fields, the project will help reduce CO2 emissions by more than 200 000 tonnes per year, corresponding to annual emissions from 100 000 private cars.

The Cost Hywind Tampen
The Hywind Tampen investment will be close to NOK 5 billion. Norwegian authorities have granted funding of up to NOK 2.3 billion through Enova. The Business Sector’s NOx fund has decided to support the project by up to NOK 566 million.

“On behalf of the partners, Equinor has awarded contracts totalling NOK 3.4 billion, subject to final project approval by Norwegian authorities. It is a plus that the oil and gas industry is competitive in renewables projects as well, and the contracts will lead to considerable spinoff effects in Norway,” said Anders Opedal, executive vice president for Technology, Projects & Drilling.

According to a study made by Multiconsult, the Hywind Tampen project is expected to create spinoff effects during the project’s life of 1 550 to 3 000 man-years for Norwegian trade and industry.

Most of the spinoff effects will occur in the project’s development phase.

The Wind Farm
The wind farm will consist of 11 wind turbines based on the Hywind wind farm concept developed by Equinor.

The 8 MW turbines will have a total capacity of 88 MW and meet about 35 per cent of the annual power demand of the five platforms, Snorre A and B and Gullfaks A, B and C.

The wind farm will be located around 140 kilometres from shore, between the Snorre and Gullfaks platforms, at a water depth of 260 to 300 metres.

Start-up in 2022
Operated from Equinor’s offices in Bergen, Hywind Tampen is scheduled for start-up at the end of 2022.



We believe that information should be free and will therefore never put up a paywall.

If you like reading our reports about the Scandinavian business scene and would like to donate towards the upkeep of the site, we would be very grateful. Click here to donate.

Most Popular Articles of November




Most Popular Articles of this Year